ID: key_26_06_02_05_09_44_13_02700 Created date: Feb 05 2026 Thursday, 6th 09:44 #주간업무
연관 문서
WFS Migration Project
Process
- 설계 및 POC 단게 (~ Mar 2025)
- 메시지 전환 (Mar ~ Mar 2026)
- F/W 검증 테스트 (Feb ~ Mar 2026)
Status
메시지 전환 (Mar ~ Mar 2026)
- Message Converted 110 or 113
- Ramining message, directly received from UI
- On going: Switch feature of UI Message (~ 12 Feb)
- UI Message will changed into OIA Message step by step
- Plan: Consider Monitoring Period after converted message, It will take 2 weeks. Target By End of Feb
F/W 검증 테스트 (Feb ~ Mar 206)
- Purpose
- To verify migrated application has enough sustainability to deploy on Production
- Aspect (측면)
- Availiability (가용성)
- Performance (성능)
- Plan
- Prepare For Test (~ 13 Feb)
- Conduct Test Case (16 ~ 20 Feb)
- Report & Tunning (23 ~ 27 Feb)
- Note
- Common
- Weekends, Line stop so that we can test it on Production Env
- Availiability
- Conduct On Dev Server
- Common
Action
Progress
연관 메일