ID: key_26_06_02_05_09_44_13_02700 Created date: Feb 05 2026 Thursday, 6th 09:44 #주간업무

연관 문서

WFS Migration Project

Process

  1. 설계 및 POC 단게 (~ Mar 2025)
  2. 메시지 전환 (Mar ~ Mar 2026)
  3. F/W 검증 테스트 (Feb ~ Mar 2026)

Status

메시지 전환 (Mar ~ Mar 2026)

  • Message Converted 110 or 113
  • Ramining message, directly received from UI
  • On going: Switch feature of UI Message (~ 12 Feb)
    • UI Message will changed into OIA Message step by step
  • Plan: Consider Monitoring Period after converted message, It will take 2 weeks. Target By End of Feb

F/W 검증 테스트 (Feb ~ Mar 206)

  • Purpose
    • To verify migrated application has enough sustainability to deploy on Production
  • Aspect (측면)
    • Availiability (가용성)
    • Performance (성능)
  • Plan
    • Prepare For Test (~ 13 Feb)
    • Conduct Test Case (16 ~ 20 Feb)
    • Report & Tunning (23 ~ 27 Feb)
  • Note
    • Common
      • Weekends, Line stop so that we can test it on Production Env
    • Availiability
      • Conduct On Dev Server

Action

Progress